Performance Insight Batch analysis dashboard: How to Start/Stop the batch?

0
Hello, I am configuring the Batchanalysis dashboard for the first time. I have already noticed that when the batch or material number changes, a new entry is displayed.Now we have a time between the batches in which the machine does not produce until a new batch is started.Since the batch and material number only change when a new batch is started, the end time of the previous batch is the same as the start time of the new batch.To change this, I set the batch and material number to “0” in the machine at the end of the batch in order to map the correct end time.However, it is now unattractive that I always have entries of a batch “0” in the dashboard.Is there another way to display the end of the batch correctly?   Best regards Steffen
asked
1 answers
0

Hello,

I'm also in touch with your regional contact via SR 1-7914332861

and we will update there.

Best regards

Matthias